RANCANGAN SEQUENCE PENAMBANGAN PADA BLOK A4 PT. ADHI KARTIKO PRATAMA DESA LAMERURU KECAMATAN LANGGIKIMA KABUPATEN KONAWE UTARA PROVINSI SULAWESI TENGGARA
DOI:
https://doi.org/10.58344/locus.v2i12.2336Keywords:
Nikel Laterit, Pit limit, SequenceAbstract
- Adhi Kartiko Pratama is a private company which operates in the nickel mining sector and has a Mining Business License covering an area of 1975 Ha. To maintain the company's production, currently PT. AKP plans to open a new mining location in Front Block A, especially in Sub Block A4, with a production target of 100,000 tons per month. This research aims to design a mining sequence based on production targets in Block A4. The design created is an estimated ore distribution. Minable reserves based on the mining pit limit design in Block A4 are 466,383.36 bcm with a total tonnage of 769,532.54 tons with an average Ni content of 1.76%, and including mining recovery parameters of 90%, it is 419,745, 02 bcm and a tonnage of 692,579.29 tons with an average Ni content of 1.74%, then the estimated mine life in Block A4 PT. Adhi Kartiko Pratama will last approximately 6 months. Based on the production target in Block A4, the mining sequence design is divided into 6 stages carried out using a level plan system or following excavation levels, where mining will start from topography with the highest level of 180 meters above sea level to topography with the lowest level of 135 meters above sea level.
References
Aryanda, Dadang, Ramli, Muhammad, & Djamaluddin, H. (2014). Perancangan Sequence penambangan batubara Untuk memenuhi target produksi bulanan. Jurnal Penelitian Geosains, 10(2).
Djunaidi, Djunaidi, & Alfitri, Alfitri. (2022). Dilema industri padat modal dan tuntutan tenaga kerja lokal. JPPI (Jurnal Penelitian Pendidikan Indonesia), 8(1), 29.
Gaspersz, Rolling Swempry. (2017). Analisis Cadangan Penambangan Batuan Gamping Pada CV Sanggaria Jaya Desa Sanggaria Arso 1 Distrik Arso Barat Kabupaten Keerom Provinsi Papua. Dinamis, 1(12), 45–51.
Hadi, Hadi, & Sepriadi, Sepriadi. (2020). A Analisis Tipe Dan Struktur Batuan Untuk Menentukan Metode Penambangan Yang Akan DigunakaN. Jurnal Teknik Patra Akademika, 11(02), 64–73.
Haryono, Ahmad Fauzan, & Aprilianta, I. Putu Eka Dimi. (2017). Perencanaan Sequence Penambangan Batubara pada Seam 16 Phase 2 di PT. KTC Coal Mining & Energy, Kec. Palaran, Samarinda, Kalimantan Timur. ReTII.
Jufri, Fadly Kurnia. (2021). Pemodelan Sebaran Kadar Ni Pada Endapan Bijih Nikel Laterit Dengan Analisis Statistik Dan Metode Inverse Distance Weighting (IDW) Untuk Perencanaan Awal Lokasi Penambangan (Studi Kasus: Blok U, PT Indrabakti Mustika, Desa Langgikima, Kabupaten Konawe Utara, Provinsi Sulawesi Tenggara). Universitas Hasanuddin.
Kaleb, Bryan J., Lengkong, Victor P. K., & Taroreh, Rita N. (2019). Penerapan Sistem Informasi Manajemen Dan Pengawasannya Di Kantor Pelayanan Pajak Pratama Manado. Jurnal EMBA: Jurnal Riset Ekonomi, Manajemen, Bisnis Dan Akuntansi, 7(1).
Negara, I. Gede Nata, & Hutapea, Ricardo O. M. (2020). Pushback Design Block X At PT Ifishdeco Southeast Sulawesi: Desain Pushback Blok X Pada Pt Ifishdeco Sulawesi Tenggara. INTAN Jurnal Penelitian Tambang, 3(2), 154–160.
Prasmoro, Alloysius Vendhi, & Hasibuan, Sawarni. (2018). Optimasi Kemampuan Produksi Alat Berat Dalam Rangka Produktifitas Dan Keberlanjutan Bisnis Pertambangan Batubara: Studi Kasus Area Pertambangan Kalimantan Timur. Jurnal Operations Excellence: Journal of Applied Industrial Engineering, 10(1), 1–16.
Purnomo, Hendro, & Wijaya, R. Andy Erwin. (2022). Pemetaan sebaran kadar Al2O3 dan RSiO2 pada endapan laterit bauksit menggunakan pendekatan metode interpolasi ordinary Kriging dan inverse distance weighting. Angkasa: Jurnal Ilmiah Bidang Teknologi, 14(1), 75–86.
Rizky, Muhammad, & Yulhendra, Dedi. (2022). Estimasi Sumber Daya Bijih Besi Menggunakan Metode Inverse Distance Weighted dan Ordinary Kriging di PT. KUATASSI, Kabupaten Solok, Sumatera Barat. Bina Tambang, 7(1), 96–106.
Setiawan, K. B. (2020). Estimasi Cadangan Batugamping Pada Kuari XIII PT. Solusi Bangun Indonesia Kabupaten Cilacap Jawa Tengah. UPN" Veteran" Yogyakarta.
Supandi, Supandi. (2015). Prediksi Umur Dinding Tambang Berdasarkan Kejadian Longsoran yang Pernah Terjadi dengan Bantuan Program Microsoft Access. Seminar Nasional Informatika (SEMNASIF), 1(1).
Wahyuni, Sri, Supriyanto, Supriyanto, & Djayus, Djayus. (2019). Estimasi Sebaran Kualitas Batubara (Ash Content) Menggunakan Metode Invers Distance Weighted (Idw) Dan Ordinary Kriging (Ok) Di Pt. Kayan Putra Utama Coal Site Separi, Kalimantan Timur. GEOSAINS KUTAI BASIN, 2(1).
Published
Issue
Section
License
Copyright (c) 2023 Jurnal Impresi Indonesia

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC-BY-SA). that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.